Hello,
Do you mean by "released cost estimate" the standard product cost estimate or the production order cost estimate? For the target costs, you only need the latter, and it does not have to be released separately, but is created by default when the order is costed. If this is not done, no costing variant is assigned to the order type in the plant-dependent data, or it is incorrect.
Many greetings,
Martin
----------------
Martin Munzel
Freelance author, SAP consultant and trainer http://www.martin-munzel.com
Do you mean by "released cost estimate" the standard product cost estimate or the production order cost estimate? For the target costs, you only need the latter, and it does not have to be released separately, but is created by default when the order is costed. If this is not done, no costing variant is assigned to the order type in the plant-dependent data, or it is incorrect.
Many greetings,
Martin
----------------
Martin Munzel
Freelance author, SAP consultant and trainer http://www.martin-munzel.com